RTW >Engineering Services > Gore Valley
Gore Valley Water Treatment Plant Rehabilitation
This 1-mgd plant was taken out of service some time ago when water treatment was regionalized. The District hired Tetra Tech RTW to evaluate the plant for possible short-term supply since the regional plant was approaching capacity. Tetra Tech RTW conducted the study and, as a result, concluded that reactivation was possible with some rehabilitation work on the plant and the associated pump station.
Tetra Tech RTW then completed construction documents for improvements to the following facilities:
- raw water infiltration gallery
- backwash and high-service pumps
- chemical feed system
- filters
- equipment painting
- building painting
Tetra Tech RTW helped the District retain a contractor and performed construction management services. The plant was on-line and operating at full capacity after the rehabilitation work was completed.
site search | contact us | help
Copyright © 2008 Rothberg, Tamburini & Winsor, Inc. (Tetra Tech RTW), A Tetra Tech Company, All Rights Reserved